PROOF OF CONCEPT ON REMEDIATION OF SEWAGE TREATMENT PLANT -
PROOF OF CONCEPT ON REMEDIATION OF SEWAGE TREATMENT PLANT -
PROOF OF CONCEPT ON REMEDIATION OF SEWAGE TREATMENT PLANT -
- It can be concluded that the water quality has been maintained as per IWK effluent standard, without aeration but using a combined treatment of bio-catalyst and installation of EBD at the perimeter of oxidation pond. With the installation of EBD, the operation of aeration can be reduced by 35% during the 6-month long POC evaluation. At the conclusion of POC trail, as much as 28% of energy bill has been reduced. This reduction of aeration time is expected to be further reduced after the POC period when the EBD system is fully remediating the wastewater. Thus, will result in a very significant reduction of energy bill to the STP operator.
- It is further concluded that the EBD is very effective for long term solution for sewage wastewater treatment. Besides remediating the effluent quality, its installation can help reduce the energy bill for the STP operator subsequently.